Burn-up chart


  • A chart displaying the current progress of the sprint and estimated time to burn down the complete product backlog.
  • Displays the value earned through all Sprints.
  • X-axis is the iterations since start of the project.
  • Y-axis is the total ‘done’ effort.
  • The green line is the total scope. The dashed line extrapolates the estimated total scope.
  • The red line is the total scope ‘done’ for each iteration. The dashed line extrapolates the estimated time required to burn down entire scope based on Scrum team’s current velocity.